10 Leading Indicators of Troubled Projects

11. Dezember 2018
Kategorien
Newsletter abonnieren

Leading indicators of troubled projects

In project management, we often talk about “lagging” and “leading” indicators. 

Lagging indicators are typically “output” oriented, easy to measure but hard to improve or influence. 
Leading indicators at the other hand are typically «input» oriented, harder to measure but easier to influence.

Let me illustrate this with a simple example. Let’s imagine you are responsible for managing a customer support team, and your goal is to resolve any high priority incidents within 48 hours. Currently, you only succeed in 70% of such incidents.

The output is easy to measure: You either solve these incidents in 48 hours or not. But how do you influence the outcome? What are the activities you must undertake to achieve the desired outcome?

For instance: Make sure your team starts working on such incidents immediately when they occur. Make sure that incidents are assigned to the right people with the right skillset and that this person isn’t already overloaded with other work.

This could be translated into the following “leading” indicators


> % of incidents not worked on for 2 hours.


> % of open incidents older than 1 day.


> % of incidents dispatched more then 3 times.


Average backlog of incidents per agent

When you would start measuring these indicators on a daily basis and focus on improving these, I would think it is extremely likely to see an improvement in reaching your goal.

Lagging Indicators for Projects

As I have written many times before, it’s essential to work actively with the organization that owns a project to define success across three levels before you start a project:

1) Project delivery success is about defining the criteria by which the process of delivering the project is successful.

Essentially this addresses the classic triangle «scope, time, budget». It is limited to the duration of the project and success can be measured as soon as the project is officially completed (with intermediary measures being taken of course as part of project control processes). 

2) Product or service success is about defining the criteria by which the product or service delivered is deemed successful.

For example, the system is used by all users in scope, uptime is 99.99%, customer satisfaction has increased by 25%, operational costs have decreased by 15%, and so on.

These criteria need to be measured once the product/service is implemented and over a defined period of time. This means it cannot be measured immediately at the end of the project itself.

3) Business success is about defining the criteria by which the product or service delivered brings value to the overall organization, and how it contributes financially and/or strategically to the business.

For example, financial value contribution (increased turnover, profit, etc.) or competitive advantage (market share won, technology advantage).

All these measures are so-called lagging indicators. A lagging indicator is a measurable fact that records the actual performance of a project. They all represent facts about the project, the resulting product/service and the benefits of it to the organization.

But things can start to go wrong in a project well before the performance measure turns the traffic light on the scorecard red.

Using metrics that measure past events is like driving while looking through the rear window. It’s easy to miss an opportunity or threat on the road ahead until you hit it.

Leading Indicators for Projects

A leading indicator is a measurable factor that changes before the project starts to follow a particular pattern or trend. Leading indicators are used to predict changes in the project, but they are not always accurate.

Examples of leading indicators for a project’s success:

1) Poorly defined (or undefined) done: Project failure starts when we can’t tell what “done” looks like in any meaningful way. Without some agreement on our vision of “done,” we’ll never recognize it when it arrives, except when we’ve run out of time or money or both.

2)  Poorly defined (or undefined) success: A project can only be successful if the success criteria are defined, ideally upfront. Therefore the lack of these definitions on the three levels as described above is a great leading indicator for project trouble.

3) Stability, quality, and availability of project team: a lot of change in the project team is a good leading indicator for trouble. The same for missing skills and experience. Also, team atmosphere is a great leading indicator.

4) Engineering practices: the practices that are implemented are a good leading indicator of engineering quality.

5) Risk management: the presence or lack of risk management is a great leading indicator of the impact of negative surprises.

6) Availability of up to date RAID lists: the quality of these lists are a great indicator for awareness of trouble. Especially your issue resolution time.

7) Engagement of stakeholders and Steering Committee: When the stakeholders do not care about your project, then why should you?

8) Runway: the burn rate of a project is a lagging indicator as it describes how many money is spent (or lost) for any period of time. The runway is a leading indicator as it predicts how long the budget would last with a specific burn rate.

9) Milestones: missing or achieving the deadline on a milestone is a lagging indicator. But it is also a leading indicator for following milestones.

10) Project size: the bigger the project, the higher the probability it fails.

All leading indicators can be used for identifying troubled projects before it is too late to do something about it. Just be aware that because a leading indicator is positive, it does not mean the final outcome will be positive. Nor will a negative leading indicator means automatically a negative outcome.

In a nutshell: Using metrics that measure past events is like driving while looking through the rear window. It’s easy to miss an opportunity or threat on the road ahead until you hit it.

When you need some guidance on how to define and measure project success, just download the Project Success Model by clicking on the image.


The Project Success Model


Tags

Das könnte Sie auch interessieren

The Five Elements of a Strong Governance Structure for Critical Projects

16. Januar 2025

Every executive has nightmares about that project—the one that spirals into an unmitigated disaster.  In general there are four ways a project can end up in a boardroom-shaking failure that can destroy value, reputations, and trust in one fell swoop. 1. The Titanic Failure: The project chugs along, oblivious to the iceberg ahead, burning millions

Weiterlesen

Why Every Critical Project Needs Independent Reviews

14. Januar 2025

«Trust, but verify.» That timeless adage applies as much to critical projects as it does to diplomacy. Without an independent review, even the best-run projects can veer off course, leaving organizations blindsided by delays, cost overruns, or outright failures. Here’s the uncomfortable truth: internal stakeholders are often too close to the project to see the

Weiterlesen

Why Every Critical Project Needs an Executive Sponsor

13. Januar 2025

Launching a critical project without an executive sponsor is like sending a ship to sea without a captain—good luck steering through the storm. Projects don’t fail because of bad intentions. They fail because of a lack of alignment, authority, and support.  That’s where the executive sponsor steps in—not just as a figurehead but as the

Weiterlesen

Why Every Critical Project Needs a Dedicated Project Manager

12. Januar 2025

Far too often, organizations assign critical projects to people who already have full-time roles or, worse, delegate management to a loosely organized team with no single point of accountability. The results? Missed deadlines, blown budgets, and a whole lot of finger-pointing. Here’s the hard truth: if the project is important, it deserves a dedicated project

Weiterlesen

Case Study 21: The Australian Securities Exchange (ASX) $250 Million CHESS Blunder

6. Januar 2025

The Australian Securities Exchange (ASX) embarked on an ambitious journey to replace its 25-year-old Clearing House Electronic Subregister System (CHESS) with a state-of-the-art, blockchain-based platform.  Initially envisioned as a groundbreaking project to enhance efficiency, security, and scalability, the CHESS replacement project quickly turned into a cautionary tale.  The initiative faced repeated delays and escalating costs

Weiterlesen

Project Recovery

2. Januar 2025

  Projects fail for a variety of reasons. Especially technology projects have a low success rate. Typically more than half of them are considered a failure. If your current in-house or outsourced software or web development project is off track, chances are I can bring the necessary input and expertise to get the job done. Troubled projects

Weiterlesen

When $100 Million Technology Projects Fail, It’s the Board’s Fault—Every Single Time

2. Januar 2025

In Switzerland, rumors suggest that both Bank Julius Bär and Raiffeisen Schweiz are grappling with failed technology projects, each costing over $100 million so far. Bank Julius Bär is reportedly trying to replace its existing core banking system for the Swiss booking center with Temenos, while Raiffeisen Schweiz is attempting to build a modern e-banking

Weiterlesen

10 Essential Questions Every Board Should Ask About Technology

16. Dezember 2024

Board members play an important role in steering organizations through the complexities of technology initiatives.  To fulfil this role effectively, it’s essential to ask the right questions that probe the strategic, operational, and risk aspects of technology projects.  Here are ten critical questions every board should consider: 1) How does this technology initiative align with

Weiterlesen

Independent Board Advisory

16. Dezember 2024

Effective boards provide clarity, governance, and oversight to steer organizations toward success. However, large technology initiatives, digital transformations, and innovation efforts often challenge even the most seasoned boards.  My Board Advisory service empowers boards and board members to navigate the complexities of modern technology decisions with confidence and precision. As a trusted advisor and experienced

Weiterlesen

Case Study 20: The $4 Billion AI Failure of IBM Watson for Oncology

7. Dezember 2024

In 2011, IBM’s Watson took the world by storm when it won the television game show Jeopardy!, showcasing the power of artificial intelligence (AI). Emboldened by this success, IBM sought to extend Watson’s capabilities beyond trivia to address real-world challenges.    Healthcare, with its complex data and critical decision-making needs, became a primary focus. Among

Weiterlesen
Next