Your Projects Should Start Slow in Order to Run Fast Later

30. June 2019
Kategorien
Subscribe to our newsletter

Your projects should start slow in order to run fast later

I am a big believer of short and fat projects and I am very vocal about it. Because of this I often get asked if I propose to fast track projects and reduce upfront work.

No, I am not. On the contrary, I think more time should be spent on upfront work.

Yes, to keep costs down and maximize benefits you should keep implementation phases short and delays small. This should not be seen as an excuse for fast-tracking projects; that is, rushing them through decision making for an early start.

For smaller projects, this might be something you can get away with, but for large technology projects all you do if you hit the ground running is fail hard. Front-end planning and validation need to be thorough before deciding to give the green light to a project, or to stop it.

You need to go slow at first (during project initiation) in order to run fast later (during project delivery).

Unfortunately, many times the situation is exactly the opposite. Front-end planning and validation is rushed, bad projects are not stopped, important projects do not get the money/ people/management attention they need, implementation phases and delays are long, costs explode, and value diminishes.

In a nutshell: Stop the madness. Start slow, and run fast later.

Tags

That could also be of interest for you

Project Failure Is Largely Misunderstood

26. November 2020

For many years, organizations, researchers, and practitioners have analyzed how to manage technology projects successfully.  Among them is the Standish Group, which regularly publishes its findings in its Chaos reports. In 1994, Standish reported a shocking project success rate of only 16 percent; another 53 percent of the projects were challenged, and 31 percent failed

Read more

User Enablement is Critical for Project Success

14. November 2020

Any system is only as good as how well it is used.  If it’s a CRM, ERP, or any other system, when users don’t know how to use the system effectively the benefits of the new system for your organization will be small, or even negative.  This means user enablement is critical to the success

Read more

The True Cost of Excluding Executives from the IT Decision Making Process

18. October 2020

Throughout the past 15 years that I’ve been working as an independent project recovery consultant and interim CIO, I have observed executives’ frustration – even exasperation – with information technology and their IT departments generally. Some of the more common refrains are:  “I don’t understand IT well enough to manage it.”  “Although they work hard,

Read more

What Executives Need to Know About Project Management

11. October 2020

I work exclusively with executives and when there is one thing that I have learned over the years is that effective executives have at least a basic understanding about project management and their roles in it.    When you look in a dictionary for the word «executive» you will find an entry similar to the

Read more

Project Inputs, Activities, Outputs, Outcomes, Impact and Results

27. September 2020

Many people and organizations seem to have serious trouble separating between the inputs, activities, outputs, outcomes, impact, and the results of a project.    This leads to lot’s of confusion, bad communication, disappointed project teams, and disappointed stakeholders.   Below you will find my take on these terms and their relevance for your project.  

Read more

Solving Your Between Problems

30. August 2020

Most executives agree with me that the biggest problems are not within roles but between roles.    Not within teams but between teams.    Not within departments but between departments.    And not within organizations but between organizations.     Such “between problems” are not assigned to anyone. Why? Because they are between.    And these

Read more

However Beautiful the Strategy, You Should Occasionally Look at the Results

6. July 2020

The title of this article is frequently credited to Winston Churchill (1874-1965), but he never said it. The saying first appears from about 1981, many years after Churchill’s lifetime.   The saying is used to stress that one needs to look at results and shouldn’t fall in love with one’s designed strategy if it doesn’t

Read more

Your Risk Matrix Is a Lie

15. June 2020

Risk management is at the core of good project management.    Or as Tim Lister says “Risk management is project management for adults”.     The standard approach is to use a risk matrix to classify project risks based on their probability and impact, then give each one a ‘risk score’ by multiplying the two numbers.

Read more

Most Good Strategies Are Not Planned

7. June 2020

Many people are discussing strategy and strategizing as if they were the sole outcome of a rational, predictable, analytical process.   But reality is often the opposite; emotional, unpredictable, and chaotic.     How organizations create and implement strategy is an area of intense debate within the strategy field.   Famous researcher on management and strategy

Read more

Is Your Strategy Bad? A Simple Checklist

26. May 2020

Recognizing good strategy is hard.    You need to understand the organization, the market(s) it is operating in, its competitors, its strengths, and its challenges.    On the other hand, recognizing bad strategy is easy.    Richard Rumlet coined the term “bad strategy” in 2007 at a short Washington, D.C., seminar on national security strategy.

Read more