How Your Rollout in Waves Can End in a Tsunami

14. November 2022
Kategorien
Newsletter abonnieren

How Your Rollout in Waves Can End in a Tsunami

Many multinational organizations are bringing larger system implementations to a screeching halt because they misunderstand what it means to do a rollout in waves. 

We’re probably all familiar with the “phased rollout”. A phased rollout means you roll a project out to all targeted users at once but don’t deploy all of its planned functionality.

A good example of this would be rolling out a new CRM system to your organization. You go live in the first phase with Contact, Client, and Opportunity Management, and Account Management and Pipeline Management follow in the second phase.

Another popular type of rollout is the so-called staged rollout (also known as a rollout in waves). A rollout in waves or stages means that all the planned functionalities will be rolled out at once, but not for all users.

A rollout in waves gives you time to analyze the system’s quality, stability, and performance against your business goals. You can then decide if you want to roll out the system to more users, wait for more data, or stop the rollout. 

A rollout in waves is one of the core building blocks of making continuous delivery a reality. Facebook, Netflix, Microsoft, Google, and similar companies all rely heavily on staged rollouts.

One wave rollout method frequently used by multinational companies for new system implementation is the rollout by country or geographical territory. 

This is the preferred approach by companies implementing a new CRM, ERP, HCM, or some other key business application. Sometimes it’s combined with a phased approach.

Rolling out in waves is usually a good idea, especially compared to a “big bang” rollout. 

But before undertaking a rollout in waves, you have to carefully consider the following three realities:

1) The moment you switch on a new system in one country, you’ll need to address a bunch of Business As Usual (BAU) activities including Release Management, Change Management, New User Training … you name it. Your users will also discover bugs in the system and/or interfaces that weren’t discovered during testing. Many of them will be critical and need to be fixed ASAP. You’ll probably find that performance issues will be more common than not. Some companies call the first few months “Hyper Care” or some equivalent, but it is nothing else as BAU. 

2) As is always the case with a new system, it won’t work completely as expected. In addition to the bugs that need to be addressed within the BAU process, you’ll have a high number of Change Requests, because only now will users realize they need additional or different functionality to do their work. Again, a number of these requests will be critical and/or urgent. Users will probably ask for many additional reports because they don’t understand the data they see in the new system. If you combine your rollout in waves with a phased rollout, you’ll need to build and test the functionalities for the next phase.

3) At the same time, you’ll want to proceed with the next waves of your rollout, and you’ll need people to work on this. Think about discovery, migration, configuration, training, etc. for each new country that needs to be onboarded. The big idea is always to have one system for everyone, but local legislation and regulations and differences in how business is done in each country will force you to implement additional Change Requests in the system.

The number-one mistake I see is that organizations allocate a single team to accomplish all of the above tasks after the first-wave rollout. This approach always fails miserably and will bring the rollout to a screeching halt.

For a successful rollout in waves, you’ll need three different teams after the first wave:  one for BAU activities, one to deliver Change Requests, and one to onboard additional waves. Some people may work on more than one team, but this really should be the exception.

You’ll need to plan and budget for these teams, hire and train people for them, and define their organizational setup. 

And you’ll need to do all of this before you go live with the first wave – not after!

In a nutshell: You will need three teams for a successful system rollout in waves.

Tags

Das könnte Sie auch interessieren

My Talk «Technology Due Diligence» @ Business Angels Switzerland

5. Dezember 2024

Last week I was invited by Business Angels Switzerland to give a talk at their Academy about Technology Due Diligence. The goal of the talk was to enable investors to determine the value and risks of technology in a startup or scaleup. Many corporate executives share this challenge with startup investors.  Technology Due Diligence (TDD) is

Weiterlesen

Independent Technology Due Diligence

29. August 2024

Technology has become the backbone of nearly every successful business. For private equity firms, venture capital investors, corporate buyers, or even startups seeking investment, understanding the true state of a company’s technology landscape is critical.  My Technology Due Diligence service provides a comprehensive, independent assessment of the technical risks, opportunities, and value of a target

Weiterlesen

Case Study 19: The $20 Billion Boeing 737 Max Disaster That Shook Aviation

20. August 2024

The Boeing 737 Max, once heralded as a triumph in aviation technology and efficiency, has since become synonymous with one of the most catastrophic failures in modern corporate history.  This case study delves deep into the intricacies of the Boeing 737 Max program—a project that was initially designed to sustain Boeing’s dominance in the narrow-body

Weiterlesen

Lies, Damned Lies, and Statistics

15. August 2024

«Lies, damned lies, and statistics» is a phrase describing the persuasive power of statistics to bolster weak arguments.  It is also sometimes used to doubt the statistics used to prove an opponent’s point. Last night I watched a startup pitching and they presented a slide with some statistics showing the effectiveness of their solution to

Weiterlesen

A Step-by-Step Guide to Business Case Validation

13. August 2024

Creating a business case is a systematic process designed to justify a proposed project, investment, or decision within a business context.  A strong business case typically includes an introduction with background information, a clear problem or opportunity statement, a detailed analysis of options, a risk assessment, a financial analysis, a proposed solution, and a high-level

Weiterlesen

Independent Business Case Review

13. August 2024

A well-validated business case is the foundation of any successful initiative. Without rigorous validation, assumptions, risks, and unrealistic projections can derail even the most promising projects.    My Business Case Review provides an objective, thorough assessment to ensure your business case is realistic, robust, and aligned with strategic goals before you commit significant resources.    

Weiterlesen

Top Ten Leading Indicators of Troubled Projects for Executives

5. August 2024

If you are a senior executive or a board member in the role of executive sponsor, project sponsor, or steering committee member it is key to recognize potential issues before they become critical.  Recognizing early warning signs can make the difference between a project’s success and failure.  Whilst lagging indicators are metrics that reflect past

Weiterlesen

Why Every Critical Project Needs a Steering Committee

28. Juli 2024

Critical projects are like Formula 1 races—you don’t just need a driver; you need a pit crew, strategists, and decision-makers ready to adapt in real time.  That’s your steering committee. Big projects come with big risks, competing priorities, and high expectations. Without a steering committee, those challenges turn into roadblocks. Decisions get delayed, alignment falters,

Weiterlesen

The Most Important Role on Any Large Transformation Project

22. Juli 2024

The most important role on a large transformation project is the project sponsor.  Not the project manager.  According to the Project Management Institute (PMI)’s 2018 Pulse of the Profession In-Depth Report, «1 in 4 organisations (26%) report that the primary cause of failed projects is inadequate sponsor support«.  By contrast, «organisations with a higher percentage

Weiterlesen

Project Trouble Assessment for Executives

17. Juli 2024

Is your project headed for trouble?  Find out! If you are a senior executive or a board member in the role of executive sponsor, project sponsor, or steering committee member it is key to recognise potential issues before they become critical. Recognising early warning signs can make the difference between a project’s success and failure.

Weiterlesen