Many Decisions Are No Decisions (And This Makes Projects Difficult)

13. Juni 2018
Kategorien
Newsletter abonnieren

Effective decision making

Again and again, I am confronted with the situation during projects that I ask for a decision on something and as an answer I get «Oh, that has been already decided…».

No, it is not. A decision has NOT been made until people know:

> the name of the person accountable for carrying it out;

> the deadline;

> the names of the people who will be affected by the decision and therefore have to know about, understand, and approve it—or at least not be strongly opposed to it; and   

> the names of the people who have to be informed of the decision, even if they are not directly affected by it.

An extraordinary number of organizational decisions run into trouble because these bases aren’t covered.

It’s just as important to review decisions periodically—at a time that’s been agreed on in advance—as it is to make them carefully in the first place. That way, a poor decision can be corrected before it does real damage.

These reviews can cover anything from the results to the assumptions underlying the decision. Such a review is especially important for the most crucial and most difficult of all decisions, the ones about hiring, firing and promoting people.

When it comes to making decisions I am of the opinion that people and organizations should use a simple decision-making process in order to make them effective.

Personally, I use the one outlined by Peter F. Drucker. In 1967, he wrote his famous article on effective decision making in The Harvard Business Review that still stands the test of time.

Drucker defines the following six steps for effective decisions.

1) Classifying the problem. Is it generic? Is it exceptional and unique? Or is it the first manifestation of a new genus for which a rule has yet to be developed?

2) Defining the problem. What are we dealing with?

3) Specifying the answer to the problem. What are the “boundary conditions”?

4) Deciding what is “right,” rather than what is acceptable, in order to meet the boundary conditions. What will fully satisfy the specifications before attention is given to the compromises, adaptations, and concessions needed to make the decision acceptable?

5) Building into the decision the action to carry it out. What does the action commitment have to be? Who has to know about it?

6) Testing the validity and effectiveness of the decision against the actual course of events. How is the decision being carried out? Are the assumptions on which it is based appropriate or obsolete?

Tags

Das könnte Sie auch interessieren

The Five Elements of a Strong Governance Structure for Critical Projects

16. Januar 2025

Every executive has nightmares about that project—the one that spirals into an unmitigated disaster.  In general there are four ways a project can end up in a boardroom-shaking failure that can destroy value, reputations, and trust in one fell swoop. 1. The Titanic Failure: The project chugs along, oblivious to the iceberg ahead, burning millions

Weiterlesen

Why Every Critical Project Needs Board Supervision

15. Januar 2025

Projects are like icebergs—what you see above the surface is just the tip. Below lies the complexity, risk, and opportunity that can sink your ship if ignored. Too often, boards treat projects like black boxes, leaving management to deliver results without sufficient oversight. This hands-off approach might work for routine initiatives, but when it comes

Weiterlesen

Why Every Critical Project Needs Independent Reviews

14. Januar 2025

«Trust, but verify.» That timeless adage applies as much to critical projects as it does to diplomacy. Without an independent review, even the best-run projects can veer off course, leaving organizations blindsided by delays, cost overruns, or outright failures. Here’s the uncomfortable truth: internal stakeholders are often too close to the project to see the

Weiterlesen

Why Every Critical Project Needs an Executive Sponsor

13. Januar 2025

Launching a critical project without an executive sponsor is like sending a ship to sea without a captain—good luck steering through the storm. Projects don’t fail because of bad intentions. They fail because of a lack of alignment, authority, and support.  That’s where the executive sponsor steps in—not just as a figurehead but as the

Weiterlesen

Why Every Critical Project Needs a Dedicated Project Manager

12. Januar 2025

Far too often, organizations assign critical projects to people who already have full-time roles or, worse, delegate management to a loosely organized team with no single point of accountability. The results? Missed deadlines, blown budgets, and a whole lot of finger-pointing. Here’s the hard truth: if the project is important, it deserves a dedicated project

Weiterlesen

When $100 Million Technology Projects Fail, It’s the Board’s Fault—Every Single Time

2. Januar 2025

In Switzerland, rumors suggest that both Bank Julius Bär and Raiffeisen Schweiz are grappling with failed technology projects, each costing over $100 million so far. Bank Julius Bär is reportedly trying to replace its existing core banking system for the Swiss booking center with Temenos, while Raiffeisen Schweiz is attempting to build a modern e-banking

Weiterlesen

Top Ten Leading Indicators of Troubled Projects for Executives

5. August 2024

If you are a senior executive or a board member in the role of executive sponsor, project sponsor, or steering committee member it is key to recognize potential issues before they become critical.  Recognizing early warning signs can make the difference between a project’s success and failure.  Whilst lagging indicators are metrics that reflect past

Weiterlesen

Why Every Critical Project Needs a Steering Committee

28. Juli 2024

Critical projects are like Formula 1 races—you don’t just need a driver; you need a pit crew, strategists, and decision-makers ready to adapt in real time.  That’s your steering committee. Big projects come with big risks, competing priorities, and high expectations. Without a steering committee, those challenges turn into roadblocks. Decisions get delayed, alignment falters,

Weiterlesen

The Most Important Role on Any Large Transformation Project

22. Juli 2024

The most important role on a large transformation project is the project sponsor.  Not the project manager.  According to the Project Management Institute (PMI)’s 2018 Pulse of the Profession In-Depth Report, «1 in 4 organisations (26%) report that the primary cause of failed projects is inadequate sponsor support«.  By contrast, «organisations with a higher percentage

Weiterlesen

Project Trouble Assessment for Executives

17. Juli 2024

Is your project headed for trouble?  Find out! If you are a senior executive or a board member in the role of executive sponsor, project sponsor, or steering committee member it is key to recognise potential issues before they become critical. Recognising early warning signs can make the difference between a project’s success and failure.

Weiterlesen