Many Decisions Are No Decisions (And This Makes Projects Difficult)

13. Juni 2018
Kategorien
Newsletter abonnieren

Effective decision making

Again and again, I am confronted with the situation during projects that I ask for a decision on something and as an answer I get «Oh, that has been already decided…».

No, it is not. A decision has NOT been made until people know:

> the name of the person accountable for carrying it out;

> the deadline;

> the names of the people who will be affected by the decision and therefore have to know about, understand, and approve it—or at least not be strongly opposed to it; and   

> the names of the people who have to be informed of the decision, even if they are not directly affected by it.

An extraordinary number of organizational decisions run into trouble because these bases aren’t covered.

It’s just as important to review decisions periodically—at a time that’s been agreed on in advance—as it is to make them carefully in the first place. That way, a poor decision can be corrected before it does real damage.

These reviews can cover anything from the results to the assumptions underlying the decision. Such a review is especially important for the most crucial and most difficult of all decisions, the ones about hiring, firing and promoting people.

When it comes to making decisions I am of the opinion that people and organizations should use a simple decision-making process in order to make them effective.

Personally, I use the one outlined by Peter F. Drucker. In 1967, he wrote his famous article on effective decision making in The Harvard Business Review that still stands the test of time.

Drucker defines the following six steps for effective decisions.

1) Classifying the problem. Is it generic? Is it exceptional and unique? Or is it the first manifestation of a new genus for which a rule has yet to be developed?

2) Defining the problem. What are we dealing with?

3) Specifying the answer to the problem. What are the “boundary conditions”?

4) Deciding what is “right,” rather than what is acceptable, in order to meet the boundary conditions. What will fully satisfy the specifications before attention is given to the compromises, adaptations, and concessions needed to make the decision acceptable?

5) Building into the decision the action to carry it out. What does the action commitment have to be? Who has to know about it?

6) Testing the validity and effectiveness of the decision against the actual course of events. How is the decision being carried out? Are the assumptions on which it is based appropriate or obsolete?

Tags

Das könnte Sie auch interessieren

Going Live Too Early Can Be Worse as Going Late

15. Februar 2021

Large transformation programs rarely collapse without warning. They collapse because the warning signs are ignored. In post-mortems, the pattern is almost always the same. The project team knows the system is not ready. The risks are visible. The defects are known. The dependencies are fragile. Nothing is hidden. And yet, the decision is made to

Weiterlesen

Another Great Leading Indicator for Future Trouble – Issue Resolution Time

10. Februar 2021

I have a very simple metric for determining the health of a project or an organization: the age of issues.  Issues are like fish; when they get old, they stink.  A sure sign of a lack of leadership and upcoming trouble is old issues or issues that take longer than necessary to resolve.  Issues are

Weiterlesen

A Great Leading Indicator for Future Trouble – Missing Milestones

31. Januar 2021

I have done quite a number of inflight reviews and post-mortems of troubled and failed large system implementation projects.  One pattern that emerges very clearly is the one of missing milestones whilst keeping the go-live date the same.  It rarely ends well. I see it again and again. Multiple important milestones are missed. Sometimes by

Weiterlesen

Can a Task Force Rescue Your Failing Project?

9. Januar 2021

We’ve all witnessed projects in trouble—the ones that required a quick and firm intervention in need of help from a task force to bring it back on track.   No executive wants to be in such a difficult situation, especially not with one of his or her own projects.   But how do we, as

Weiterlesen

How a Transformation Office Can Help Your Transformation Initiatives Succeed

2. Januar 2021

A new year has just started, but also in 2021 companies will be talking about digital transformation often. I think digital transformation is a terrible description for what is just another transformation. See my article “Digital Strategy Does Not Exist” on why that is.    But we shall use the term for a moment to

Weiterlesen

Project ≠ Program ≠ Portfolio ≠ Strategy

13. Dezember 2020

I have had many heated discussions around these terms. People mix these up and it confuses your organization and its people.  This is my take on it.  If your organization is running many projects at the same time it is impossible to make the right decisions if all projects are performed in isolation. Therefore projects

Weiterlesen

Project Failure Is Largely Misunderstood

26. November 2020

For many years, organizations, researchers, and practitioners have analyzed how to manage technology projects successfully.  Among them is the Standish Group, which regularly publishes its findings in its Chaos reports. In 1994, Standish reported a shocking project success rate of only 16 percent; another 53 percent of the projects were challenged, and 31 percent failed

Weiterlesen

User Enablement is Critical for Project Success

14. November 2020

Systems do not create value. Usage does. You can implement the most advanced CRM, ERP, or core system on the market. If your organization does not use it properly, the return will be marginal at best and negative at worst. Data quality drops, processes fragment, workarounds emerge, and the old ways of working quietly reappear

Weiterlesen

When IT Owns Business Decisions, Value Disappears

18. Oktober 2020

Executives do not struggle with IT because they do not understand technology. They struggle because they have delegated decisions they should never have delegated in the first place. The frustration is familiar. Technology costs keep rising. Capabilities expand. Programs consume time and attention. And yet, the business impact remains unclear or disappointing. Systems go live,

Weiterlesen

What Executives Need to Know About Project Management

11. Oktober 2020

I work exclusively with executives and when there is one thing that I have learned over the years is that effective executives have at least a basic understanding about project management and their roles in it.    When you look in a dictionary for the word «executive» you will find an entry similar to the

Weiterlesen