The Biggest Mistake Organizations Make With Project Cost Management

17. April 2019
Kategorien
Newsletter abonnieren

The biggest mistake project managers make with project cost management

The biggest mistake organizations make with project cost management is not doing monthly forecasting and controlling.

Project cost management is nothing more than doing the following three things every month:

1) Cost Estimating
2) Cost Budgeting
3) Cost Controlling

You start your project with an approved budget. When you are lucky, you created the budget yourself based on a combination of bottom-up and top-down estimations and it got approved by the project sponsor. When you are not so lucky, you inherited a budget created by somebody else, or you just got less money than you budgeted.

The first step is taking this budget and dividing it into meaningful spending categories. The first split I always make is between internal costs and external costs. External costs are cash out, and they’re handled differently by your company than internal costs. The rest of my splits depend on project type and size, for example: project management, technology management, change management, training and travel costs. In theory this would give me a total of 10 (2 x 5) spending categories, but since travel costs are always external costs it would be effectively nine categories.

It’s important to verify that you can map your actual booked costs to these categories. This means, for internal costs, that people working on a project have different booking codes for the different categories, or you can map all the hours of one person to one category. For external costs it means that you have different booking codes for each category, or you map them manually.

Now that you have your categories, you just create a simple spreadsheet and create a simple table with a row for each category and one column for each month of the planned duration of your project. Before your project has started, you’ll fill each column with the forecasted costs per month per category. When your project has already been running for a while, you will place the actual booked costs per category for these months in the columns and the forecast values in the rest.

When you have done this, you can add the following six columns to the end of the table.

> Total Budget: Here you manually input the budget you have per category.

> Total Actuals: This is the sum of all booked costs per category.

> Total Forecast: This is the sum of all forecasted costs per category.

> Projected Costs: This is the sum of Total Actuals + Total Forecast per category.

> Budget – Actuals: This gives you the amount that you have left of your budget per category.

> Budget – Projected Costs: This gives you a good indication if your budget is enough to realize the project.

Now add one row to your table that just sums up all the rows above, so you have the information per category as well as on a project level.

This spreadsheet is all you need as a tool to start effective project cost management.

No matter your starting point and categories, from now on you have to do the following four things each and every month until the project is officially closed.

1) Get all the costs that are booked on your project from your finance team. Put these numbers in the month they are booked. Remember that these are booked later as they have occurred.

2) Add so-called accruals to your forecast. When Supplier A has worked 36 man-days on your project in April, then you need to add these as accruals to the forecast for May. When they are not booked, then you will add the accruals to the forecast from June. You do this until the final invoice is booked and the number shows up in your actual booked costs. This is an essential part of cost controlling. When you do not do this, you will always have around two months of external costs not in your overview and will be very surprised at the end of your project.

3) Update your forecast based on what you have learned this month about the project and update these numbers in the spreadsheet.

4) Review the new numbers in the last six columns and take the necessary actions based on them.

When it comes down to it, project cost management is nothing more than discipline to break down the spending categories, create an effective spreadsheet, and do the cost estimating, cost budgeting, and cost controlling steps described above every single month, and the ability of the organization to produce the input needed. The better the quality of the input, the better the quality of your cost controlling.

In a nutshell: The key to project cost management is monthly forecasting and controlling.

When you need some guidance on how to define and measure project success, just download the Project Success Model by clicking on the image.


The Project Success Model


Tags

Das könnte Sie auch interessieren

The Professional Services Transformation Paradox #11 – Risk Mitigation vs. Innovation

7. Mai 2026

Professional services firms are designed to minimize risk. Their business model depends on trust, reputation, and consistency. Clients rely on them for assurance, judgment, and reliability, which means failure is not just a delivery issue, but a firm-level risk. A single incident can have disproportionate consequences, whether through litigation, regulatory scrutiny, or reputational damage. That

Weiterlesen

The Professional Services Transformation Paradox #10 – Client Intimacy vs. Platform Standardization

28. April 2026

Professional services firms win through relationships. The closer they are to the client, the more value they create. Understanding the client’s context, adapting to their needs, shaping solutions around specific situations rather than applying generic ones. That is where trust is built, where differentiation happens, and where premium pricing becomes possible. Standardization moves in the

Weiterlesen

The Professional Services Transformation Paradox #8 – Short-Term Revenue vs. Long-Term Capability

23. April 2026

Professional services firms are built around revenue. Revenue is visible, measurable, and immediate. It drives partner compensation, signals performance, and anchors decision-making across the firm. Every client won, every project sold, every hour billed translates directly into current-year outcomes. Capability building works differently. It requires investment upfront, often without immediate return, and pays off over

Weiterlesen

The Professional Services Transformation Paradox #7 – Partner Autonomy vs. Firm-Level Strategy

18. April 2026

One of the defining features of professional services firms is partner autonomy. Partners are expected to build and run their own business. They originate clients, grow revenue, manage teams, and are rewarded based on the performance of what they directly control. This creates strong ownership, high accountability, and a culture where individual success is tightly

Weiterlesen

The Professional Services Transformation Paradox #6 – Service Lines vs. Firm

16. April 2026

One of the most persistent illusions in professional services is the idea of “one firm.” From the outside, large firms present themselves as unified organizations. One brand, one client proposition, one set of capabilities delivered across audit, tax, advisory, and deals. The expectation is clear: if the firm is integrated in the market, it should

Weiterlesen

The Professional Services Transformation Paradox #5 – Global Standardization vs. Local Economics

12. April 2026

One of the least discussed challenges in large transformation programs is the illusion of standardization. From the outside, global professional services firms look highly uniform. One brand, one set of services, one methodology, delivered across countries in a way that suggests consistency and control. Audit, tax, consulting, deals all appear to operate within the same

Weiterlesen

The Professional Services Transformation Paradox #4 – Accountability vs. Alignment

1. April 2026

In large transformation programs, accountability is rarely missing. It is distributed. It sits with executive sponsors, steering committees, transformation offices, service line leaders, and partner groups, each with a defined role and a legitimate claim to involvement. On paper, this creates alignment. In practice, it often removes ownership, because when accountability is spread across too

Weiterlesen

The Professional Services Transformation Paradox #3 – Long-Term Investment vs. Short-Term Management

27. März 2026

One of the most underestimated constraints in professional services transformation is not technology, capability, or even funding. It is time. Real transformation takes longer than most firms are structurally able to tolerate. Core systems such as ERP platforms, data architectures, AI capabilities, or global workflow solutions are not incremental improvements. They are foundational changes. They

Weiterlesen

The Professional Services Transformation Paradox #2 – Internal vs. Client Execution

26. März 2026

One of the most persistent, and least openly discussed, tensions in professional services firms lies in how they execute their own transformations. It is a tension that does not reveal itself in strategy decks or partner presentations, but in the day-to-day reality of large internal programs that quietly struggle to deliver. At first glance, the

Weiterlesen

The Professional Services Transformation Paradox #1 – Technology Alliances vs. Internal Fit

20. März 2026

This article is part of a series exploring the tensions at the core of the Professional Services Transformation Paradox. The paradox itself is straightforward, yet deeply consequential. Firms that excel at transforming their clients often struggle to transform themselves. Not because they lack capability, but because their own structures, incentives, and operating models create resistance

Weiterlesen
Next