What Is the Real Value of Your Technology Project?

1. Dezember 2019
Kategorien
Newsletter abonnieren

What Is the Real Value of Your Technology Project?In order to assess project opportunities and make difficult trade-off and priority decisions about where to focus your limited resources, you need to be able to compare projects on a like-for-like basis.

And since there’s just no getting around the fundamental challenge that all organizations should be sustaining themselves, at some point the projects we invest in should create value.

Therefore, you should make project valuation — estimating the value of your projects — a part of your decision-making process.

So what is the value of a project? It’s simple:

Value = Benefits − Costs

In previous articles I discussed estimating project costs (see “What Are the Real Costs of Your Technology Project?”) and project benefits (see “What Are the Real Benefits of Your Technology Project?”).

If you have both the costs and benefits of your project in dollars, the computation of value is very straightforward.

But what this definition is completely ignoring is time. And time has a major impact on the value of a project.

Let’s take two projects, A and B, as an example. All figures are expressed in thousands of U.S. dollars.

Project A
        
Year
1
2
3
4
5
6
7
Total
Costs
800
100
100
100
100
100
100
1400
Benefits
400
500
400
300
300
200
200
2300
Project B
        
Year
1
2
3
4
5
6
7
Total
Costs
2000
1000
1000
1000
500
500
500
6500
Benefits
0
0
3000
3000
2000
1500
1000
10500

Now we will have a look at how time influences the value of these projects.

Measurement Period 

Let’s take one of the most used project valuation methods as an example: return on investment (ROI).

Return on investment (ROI) is a performance measure used to evaluate the efficiency of an investment or to compare the efficiency of a number of different investments. ROI tries to directly measure the amount of return on a particular investment, relative to the investment’s cost.

To calculate ROI, the benefit (or return) of an investment is divided by the cost of the investment. The result is expressed as a percentage or a ratio. In our case, the investment is our project. The return on investment formula is as follows:

ROI = (Current Value of Investment − Cost of Investment) / Cost of Investment

When we apply this formula to our project A we will get the following result:

Project A
       
Year
1
2
3
4
5
6
7
Accrued Costs
800
900
1000
1100
1200
1300
1400
Accrued Benefits
400
900
1300
1600
1900
2100
2300
Value
-400
0
300
500
700
800
900
ROI
-50.00%
0.00%
30.00%
45.45%
58.33%
61.54%
64.29%
 

And for project B we get:

Project B
       
Year
1
2
3
4
5
6
7
Accrued Costs
2000
3000
4000
5000
5500
6000
6500
Accrued Benefits
0
0
3000
6000
8000
9500
10500
Value
-2000
-3000
-1000
1000
2500
3500
4000
ROI
-100.00%
-100.00%
-25.00%
20.00%
45.45%
58.33%
61.54%

You see that, depending on what year you use for measuring your ROI, the results are totally different.

Time to Value

The time to value (TTV) measures the length of time necessary to finish a project and start the realization of the benefits of the project. One project valuation method incorporating this concept is the payback period (PB).

The payback period refers to the amount of time it takes to recover the cost of an investment. Simply put, the payback period is the length of time until an investment reaches a break-even point. The desirability of an investment is directly related to its payback period. Shorter paybacks mean more attractive investments.

When we look again at Project A and Project B you see a massive difference in the payback period.

Project A has a payback period of 24 months, and Project B has a payback period of 42 months.

Time Value of Money

There is one problem with the payback period: It ignores the time value of money (TVM). 

TVM is the concept that money available at the present time is worth more than the identical sum in the future due to its potential earning capacity. This core principle of finance holds that, provided money can earn interest, any amount of money is worth more the sooner it is received. TVM is also sometimes referred to as present discounted value. 

That is why some project valuation methods include the TVM aspect. For example, internal rate of return (IRR) and net present value (NPV).

Net present value (NPV) is the difference between the present value of cash inflows and the present value of cash outflows over a period of time. NPV is used in capital budgeting and investment planning to analyze the profitability of a projected investment or project.

The following formula is used to calculate NPV:
What Is the Real Value of Your Technology Project?

As you can see, the higher your rate of return “r” is, the lower the current value of your project. Typically the value for “r” is determined by management.

The internal rate of return (IRR) is the discount rate that makes the net present value (NPV) of all cash flows from a particular project equal to zero. IRR calculations rely on the same formula as NPV does.

To calculate IRR using the formula, one would set NPV equal to zero and solve for the discount rate (r), which is the IRR. Because of the nature of the formula, however, IRR cannot be calculated analytically and must instead be calculated either through trial and error or using software programmed to calculate IRR.

Generally speaking, the higher a project’s internal rate of return, the more desirable it is to undertake. IRR is uniform for investments of varying types and, as such, it can be used to rank multiple prospective projects on a relatively even basis. 

Assuming the costs of investment are equal among the various projects, the project with the highest IRR would probably be considered the best and be undertaken first.

Cost of Delay

Cost of delay (CoD) is a key metric that represents the economic impact of a delay in project delivery. It is a way of communicating the impact of time on the outcomes we hope to achieve. More formally, it is the partial derivative of the total expected value with respect to time.

CoD combines urgency and value — two things that humans are not very good at distinguishing between. To make good decisions, we need to understand not just how valuable something is, but also how urgent it is.

I discussed CoD in detail in the article “What Is the Real Cost of Delay of Your Project?”. Depending on your urgency profile, your project end date can have a significant impact on the value of the project.

So what is the real value of your project? 

As we have seen in this article, the value of a project is determined by its benefits, costs, duration, and urgency. Putting it all together leads to the following diagram.
What Is the Real Value of Your Technology Project?

An ideal project valuation method is one where all metrics will indicate the same decision.

Unfortunately, the approaches mentioned above will often produce contradictory results.


Depending on management’s preferences, your economic situation, and selection criteria, more emphasis should be put on one metric over another.

As explained above, there are common advantages and disadvantages associated with these widely used project valuation methods.

Nonetheless, you should use one or more of them in your selection process.


In a nutshell: Determining the dollar value of your projects is essential for selecting the right one. Value = Benefits − Costs, and is dependent on duration and urgency.
Tags

Das könnte Sie auch interessieren

The Professional Services Transformation Paradox #11 – Risk Mitigation vs. Innovation

7. Mai 2026

Professional services firms are designed to minimize risk. Their business model depends on trust, reputation, and consistency. Clients rely on them for assurance, judgment, and reliability, which means failure is not just a delivery issue, but a firm-level risk. A single incident can have disproportionate consequences, whether through litigation, regulatory scrutiny, or reputational damage. That

Weiterlesen

The Professional Services Transformation Paradox #10 – Client Intimacy vs. Platform Standardization

28. April 2026

Professional services firms win through relationships. The closer they are to the client, the more value they create. Understanding the client’s context, adapting to their needs, shaping solutions around specific situations rather than applying generic ones. That is where trust is built, where differentiation happens, and where premium pricing becomes possible. Standardization moves in the

Weiterlesen

The Professional Services Transformation Paradox #8 – Short-Term Revenue vs. Long-Term Capability

23. April 2026

Professional services firms are built around revenue. Revenue is visible, measurable, and immediate. It drives partner compensation, signals performance, and anchors decision-making across the firm. Every client won, every project sold, every hour billed translates directly into current-year outcomes. Capability building works differently. It requires investment upfront, often without immediate return, and pays off over

Weiterlesen

The Professional Services Transformation Paradox #7 – Partner Autonomy vs. Firm-Level Strategy

18. April 2026

One of the defining features of professional services firms is partner autonomy. Partners are expected to build and run their own business. They originate clients, grow revenue, manage teams, and are rewarded based on the performance of what they directly control. This creates strong ownership, high accountability, and a culture where individual success is tightly

Weiterlesen

The Professional Services Transformation Paradox #6 – Service Lines vs. Firm

16. April 2026

One of the most persistent illusions in professional services is the idea of “one firm.” From the outside, large firms present themselves as unified organizations. One brand, one client proposition, one set of capabilities delivered across audit, tax, advisory, and deals. The expectation is clear: if the firm is integrated in the market, it should

Weiterlesen

The Professional Services Transformation Paradox #5 – Global Standardization vs. Local Economics

12. April 2026

One of the least discussed challenges in large transformation programs is the illusion of standardization. From the outside, global professional services firms look highly uniform. One brand, one set of services, one methodology, delivered across countries in a way that suggests consistency and control. Audit, tax, consulting, deals all appear to operate within the same

Weiterlesen

The Professional Services Transformation Paradox #4 – Accountability vs. Alignment

1. April 2026

In large transformation programs, accountability is rarely missing. It is distributed. It sits with executive sponsors, steering committees, transformation offices, service line leaders, and partner groups, each with a defined role and a legitimate claim to involvement. On paper, this creates alignment. In practice, it often removes ownership, because when accountability is spread across too

Weiterlesen

The Professional Services Transformation Paradox #3 – Long-Term Investment vs. Short-Term Management

27. März 2026

One of the most underestimated constraints in professional services transformation is not technology, capability, or even funding. It is time. Real transformation takes longer than most firms are structurally able to tolerate. Core systems such as ERP platforms, data architectures, AI capabilities, or global workflow solutions are not incremental improvements. They are foundational changes. They

Weiterlesen

The Professional Services Transformation Paradox #2 – Internal vs. Client Execution

26. März 2026

One of the most persistent, and least openly discussed, tensions in professional services firms lies in how they execute their own transformations. It is a tension that does not reveal itself in strategy decks or partner presentations, but in the day-to-day reality of large internal programs that quietly struggle to deliver. At first glance, the

Weiterlesen

The Professional Services Transformation Paradox #1 – Technology Alliances vs. Internal Fit

20. März 2026

This article is part of a series exploring the tensions at the core of the Professional Services Transformation Paradox. The paradox itself is straightforward, yet deeply consequential. Firms that excel at transforming their clients often struggle to transform themselves. Not because they lack capability, but because their own structures, incentives, and operating models create resistance

Weiterlesen
Next