When is your Project Backlog Item "Ready" for selection?

26. Juli 2017
Kategorien
Newsletter abonnieren

As defined in the Simple Portfolio Management Framework, the Project Backlog is an ordered list of all projects that might be needed in the organization and is the single source of projects for any changes to be made in the organization. The Portfolio Owner is responsible for the Project Backlog, including its content, availability, and ordering.

The Project Backlog lists all projects, ideas, proposals, enhancements, and fixes that constitute the changes to be made to the organization in the future. See my article on Demand Management for ideas on how to collect all these ideas.

 A Project Backlog is never complete. The earliest development of it only lays out the initially known and best-understood projects. The Project Backlog evolves as the organization and the environment in which it operates evolves. The Project Backlog is dynamic; it constantly changes to identify what the organization needs to be appropriate, competitive, and useful. As long as an organization exists, its Project Backlog also exists.

Project Backlog refinement is the act of adding detail, estimates, and order to items in the Project Backlog. This is an ongoing process in which the Product Owner and the PMO Team collaborate on the details of Project Backlog items. During Project Backlog refinement, items are reviewed and revised. The Portfolio Team decides how and when refinement is done. Refinement usually consumes 50% of the capacity of the Portfolio Owner and PMO Team. However, Project Backlog items can be updated at any time by the Product Owner or at the Product Owner’s discretion.

Higher ordered Project Backlog items are usually clearer and more detailed than lower ordered ones. More precise estimates are made based on the greater clarity and increased detail; the lower the order, the less detail. Project Backlog items that will occupy the Portfolio Team for the upcoming Portfolio Cycle are refined so that any one item can be decided on within the Portfolio Planning Meeting. Project Backlog items that can be decided on by the Portfolio Team within a Portfolio Planning Meeting are deemed “Ready” for selection in a Portfolio Planning. Project Backlog items usually acquire this degree of transparency through the above-described refining activities.

The Project Backlog Item

Depending on your organization and your portfolio you will need different information for your Project Backlog Items to make the right decisions. But my experience has shown that the list below will give you a good start.

Sponsorship
Who would be the project sponsor?
Finance
What are the estimated costs? Estimate the following:  
1. Project costs: internal and cash-out
2. Yearly operational costs
3. Total Cost of Ownership for 5 years (or shorter when the life expectancy of the project result is shorter)

As explained in our article on Categorization the most effective estimates for the Project Backlog are Range Based Estimates.

Driver
What business problem does the project solve?
Strategy alignment
Which strategic goals does this project align with? See the article on Categorization on how to link project backlog items with strategy. Add regulatory/compliance and operational as an option as well.
Risk
Describe what is the impact of not doing this project?
Describe what is the risk of doing this project?
Give one risk valuation High, Medium, Low for use in the risk-value portfolio bubble chart.
Benefits
What is the value of this project to the organization? Express in CHF as well describing in text. List the expected benefits.
Success metrics
How will we measure success? For example:
– Stakeholder satisfaction
– Customer satisfaction
– Quality delivered to the customer
– Return on Investment
– Meeting business case objectives
– Customer adoption
– Meeting governance criteria
– Benefits realization
Full scope, on time and in budget has nothing to do with success! It just tells you something about the quality of your estimations, not the results of your project.
Culture
Is the organization culture right for this kind of project? Describe and give a valuation Yes or No. 
Technology
Do we bring in new technology in-house or do we build with and upon existing technology? Describe and give a valuation. A categorization that I have used many times is the following: 1) Technology exists in the organization, 2) Technology is easily acquired, 3) Technology is hard to acquire, 4) Technology needs to be created, 5) No technology needed
Approach
Would we buy or make?
Time criticality
Should it be executed in a certain timeframe in order to give benefits? Describe and give a valuation Yes or No.
Client Impact
Would there be a lot of change for our clients? Discontinuing a service could have a very high impact for some Clients. Describe and give one valuation High, Medium or Low.
Employee Impact
Would there be a lot of change for our employees? For example, a new ERP system would have a very high Impact. Describe and give one valuation High, Medium or Low.
Training
Will staff training be required? Add to costs!
Portfolio
How does this project link to other projects in the portfolio? Dependencies? Shared platforms? Double work? Describe.

The moment you have collected the information above you are «Ready» for evaluation and possible selection of this project for your portfolio.

Tags

Das könnte Sie auch interessieren

The Five Elements of a Strong Governance Structure for Critical Projects

16. Januar 2025

Every executive has nightmares about that project—the one that spirals into an unmitigated disaster.  In general there are four ways a project can end up in a boardroom-shaking failure that can destroy value, reputations, and trust in one fell swoop. 1. The Titanic Failure: The project chugs along, oblivious to the iceberg ahead, burning millions

Weiterlesen

Why Every Critical Project Needs Independent Reviews

14. Januar 2025

«Trust, but verify.» That timeless adage applies as much to critical projects as it does to diplomacy. Without an independent review, even the best-run projects can veer off course, leaving organizations blindsided by delays, cost overruns, or outright failures. Here’s the uncomfortable truth: internal stakeholders are often too close to the project to see the

Weiterlesen

Why Every Critical Project Needs an Executive Sponsor

13. Januar 2025

Launching a critical project without an executive sponsor is like sending a ship to sea without a captain—good luck steering through the storm. Projects don’t fail because of bad intentions. They fail because of a lack of alignment, authority, and support.  That’s where the executive sponsor steps in—not just as a figurehead but as the

Weiterlesen

Why Every Critical Project Needs a Dedicated Project Manager

12. Januar 2025

Far too often, organizations assign critical projects to people who already have full-time roles or, worse, delegate management to a loosely organized team with no single point of accountability. The results? Missed deadlines, blown budgets, and a whole lot of finger-pointing. Here’s the hard truth: if the project is important, it deserves a dedicated project

Weiterlesen

Case Study 21: The Australian Securities Exchange (ASX) $250 Million CHESS Blunder

6. Januar 2025

The Australian Securities Exchange (ASX) embarked on an ambitious journey to replace its 25-year-old Clearing House Electronic Subregister System (CHESS) with a state-of-the-art, blockchain-based platform.  Initially envisioned as a groundbreaking project to enhance efficiency, security, and scalability, the CHESS replacement project quickly turned into a cautionary tale.  The initiative faced repeated delays and escalating costs

Weiterlesen

Project Recovery

2. Januar 2025

  Projects fail for a variety of reasons. Especially technology projects have a low success rate. Typically more than half of them are considered a failure. If your current in-house or outsourced software or web development project is off track, chances are I can bring the necessary input and expertise to get the job done. Troubled projects

Weiterlesen

When $100 Million Technology Projects Fail, It’s the Board’s Fault—Every Single Time

2. Januar 2025

In Switzerland, rumors suggest that both Bank Julius Bär and Raiffeisen Schweiz are grappling with failed technology projects, each costing over $100 million so far. Bank Julius Bär is reportedly trying to replace its existing core banking system for the Swiss booking center with Temenos, while Raiffeisen Schweiz is attempting to build a modern e-banking

Weiterlesen

10 Essential Questions Every Board Should Ask About Technology

16. Dezember 2024

Board members play an important role in steering organizations through the complexities of technology initiatives.  To fulfil this role effectively, it’s essential to ask the right questions that probe the strategic, operational, and risk aspects of technology projects.  Here are ten critical questions every board should consider: 1) How does this technology initiative align with

Weiterlesen

Independent Board Advisory

16. Dezember 2024

Effective boards provide clarity, governance, and oversight to steer organizations toward success. However, large technology initiatives, digital transformations, and innovation efforts often challenge even the most seasoned boards.  My Board Advisory service empowers boards and board members to navigate the complexities of modern technology decisions with confidence and precision. As a trusted advisor and experienced

Weiterlesen

Case Study 20: The $4 Billion AI Failure of IBM Watson for Oncology

7. Dezember 2024

In 2011, IBM’s Watson took the world by storm when it won the television game show Jeopardy!, showcasing the power of artificial intelligence (AI). Emboldened by this success, IBM sought to extend Watson’s capabilities beyond trivia to address real-world challenges.    Healthcare, with its complex data and critical decision-making needs, became a primary focus. Among

Weiterlesen
Next