Your Projects Should Start Slow in Order to Run Fast Later

30. Juni 2019
Kategorien
Newsletter abonnieren

Your projects should start slow in order to run fast later

I am a big believer of short and fat projects and I am very vocal about it. Because of this I often get asked if I propose to fast track projects and reduce upfront work.

No, I am not. On the contrary, I think more time should be spent on upfront work.

Yes, to keep costs down and maximize benefits you should keep implementation phases short and delays small. This should not be seen as an excuse for fast-tracking projects; that is, rushing them through decision making for an early start.

For smaller projects, this might be something you can get away with, but for large technology projects all you do if you hit the ground running is fail hard. Front-end planning and validation need to be thorough before deciding to give the green light to a project, or to stop it.

You need to go slow at first (during project initiation) in order to run fast later (during project delivery).

Unfortunately, many times the situation is exactly the opposite. Front-end planning and validation is rushed, bad projects are not stopped, important projects do not get the money/ people/management attention they need, implementation phases and delays are long, costs explode, and value diminishes.

In a nutshell: Stop the madness. Start slow, and run fast later.

Tags

Das könnte Sie auch interessieren

The Five Elements of a Strong Governance Structure for Critical Projects

16. Januar 2025

Every executive has nightmares about that project—the one that spirals into an unmitigated disaster.  In general there are four ways a project can end up in a boardroom-shaking failure that can destroy value, reputations, and trust in one fell swoop. 1. The Titanic Failure: The project chugs along, oblivious to the iceberg ahead, burning millions

Weiterlesen

Why Every Critical Project Needs Independent Reviews

14. Januar 2025

«Trust, but verify.» That timeless adage applies as much to critical projects as it does to diplomacy. Without an independent review, even the best-run projects can veer off course, leaving organizations blindsided by delays, cost overruns, or outright failures. Here’s the uncomfortable truth: internal stakeholders are often too close to the project to see the

Weiterlesen

Why Every Critical Project Needs an Executive Sponsor

13. Januar 2025

Launching a critical project without an executive sponsor is like sending a ship to sea without a captain—good luck steering through the storm. Projects don’t fail because of bad intentions. They fail because of a lack of alignment, authority, and support.  That’s where the executive sponsor steps in—not just as a figurehead but as the

Weiterlesen

Why Every Critical Project Needs a Dedicated Project Manager

12. Januar 2025

Far too often, organizations assign critical projects to people who already have full-time roles or, worse, delegate management to a loosely organized team with no single point of accountability. The results? Missed deadlines, blown budgets, and a whole lot of finger-pointing. Here’s the hard truth: if the project is important, it deserves a dedicated project

Weiterlesen

Case Study 21: The Australian Securities Exchange (ASX) $250 Million CHESS Blunder

6. Januar 2025

The Australian Securities Exchange (ASX) embarked on an ambitious journey to replace its 25-year-old Clearing House Electronic Subregister System (CHESS) with a state-of-the-art, blockchain-based platform.  Initially envisioned as a groundbreaking project to enhance efficiency, security, and scalability, the CHESS replacement project quickly turned into a cautionary tale.  The initiative faced repeated delays and escalating costs

Weiterlesen

Project Recovery

2. Januar 2025

  Projects fail for a variety of reasons. Especially technology projects have a low success rate. Typically more than half of them are considered a failure. If your current in-house or outsourced software or web development project is off track, chances are I can bring the necessary input and expertise to get the job done. Troubled projects

Weiterlesen

When $100 Million Technology Projects Fail, It’s the Board’s Fault—Every Single Time

2. Januar 2025

In Switzerland, rumors suggest that both Bank Julius Bär and Raiffeisen Schweiz are grappling with failed technology projects, each costing over $100 million so far. Bank Julius Bär is reportedly trying to replace its existing core banking system for the Swiss booking center with Temenos, while Raiffeisen Schweiz is attempting to build a modern e-banking

Weiterlesen

10 Essential Questions Every Board Should Ask About Technology

16. Dezember 2024

Board members play an important role in steering organizations through the complexities of technology initiatives.  To fulfil this role effectively, it’s essential to ask the right questions that probe the strategic, operational, and risk aspects of technology projects.  Here are ten critical questions every board should consider: 1) How does this technology initiative align with

Weiterlesen

Independent Board Advisory

16. Dezember 2024

Effective boards provide clarity, governance, and oversight to steer organizations toward success. However, large technology initiatives, digital transformations, and innovation efforts often challenge even the most seasoned boards.  My Board Advisory service empowers boards and board members to navigate the complexities of modern technology decisions with confidence and precision. As a trusted advisor and experienced

Weiterlesen

Case Study 20: The $4 Billion AI Failure of IBM Watson for Oncology

7. Dezember 2024

In 2011, IBM’s Watson took the world by storm when it won the television game show Jeopardy!, showcasing the power of artificial intelligence (AI). Emboldened by this success, IBM sought to extend Watson’s capabilities beyond trivia to address real-world challenges.    Healthcare, with its complex data and critical decision-making needs, became a primary focus. Among

Weiterlesen
Next